Displaying items by tag: Order
Singapore: Jurong Port has ordered three Siwertell ship unloaders from Bruks Siwertell to handle cement imports. The port’s cement terminal already has three Siwertell ship unloaders that have been used for over 20 years. Two of these will be replaced as part of the upgrade project.
The three new ST 490-M screw-type rail-travelling unloaders will each discharge cement, fly ash and cement slag from vessels up to 50,000dwt at a continuous rated capacity of 800t/hr. Two of the new unloaders are scheduled for delivery in May 2022 and the third by the end of 2022. All will be fully assembled prior to delivery and transported by heavy-lift ship. Final commissioning and performance tests will be carried out in Jurong Port.
North Africa: Turkey-based DAL Engineering Group has announced that it has acted upon a contract to design and manufacture a ball mill for a grinding plant project. It shipped the 3.0m x 10m mill to a grinding plant in North Africa in June 2020.
Gebr. Pfeiffer provides update on modular mill for Petra Cement plant in the Philippines
08 July 2020Philippines: Germany-based Gebr. Pfeiffer says a ready2grind system it supplied to Petra Cement started in early December 2019. The clinker grinding mill is operational at a grinding plant on the Zamboanga Peninsula in Mindanao. No value for the order has been disclosed. Petra Cement’s sister company , Big Boss Cement, has also ordered a modular mill system from Gebr. Pfeiffer.
Germany/Vietnam: Loesche says that it has dispatched two LM 53.3+3 CS vertical roller mills from its plant in North Rhine-Westphalia for a new line at Thanh Thang Group Cement’s integrated Bong Lang cement plant. The mills have a combined capacity of 180t/hr and grind clinker to a fineness of 4000 Blaine. The new line, installed by Sinoma-NCDRI, will be commissioned in late-2021. Loesche will also supply two cellular wheel feeders, metal detectors and sealing air blowers.
Nigeria: Denmark-based FLSmidth has secured a contract with Dangote Cement for the supply of hot kiln alignment services for 16 kiln lines across Africa. 10 of the lines are installed across three plants in Nigeria, with the remaining six situated in Republic of the Congo, Ethiopia, South Africa, Tanzania and Zambia. The contract will endure until 2026.
Dangote Cement said that it chose FLSmidth to help it achieve ‘uninterrupted cement production and dispatch around the clock. Dangote Group deputy managing director Arvind Pathak said, “The equipment health audits, services, and support extended by FLSmidth have helped us maintain our pyro process equipment with good reliability. Hot kiln alignment is an excellent preventative maintenance strategy.”
FLSmidth says that it conducts 250 hot kiln alignments worldwide annually.
Philippines: Gebr. Pfeiffer has received an order for a modular four-roller ready2grind 2500 vertical grinding unit to Big Boss Cement’s Porac, Pampanga plant. It says that the mill will have a production capacity of 70t/hr of cement, ground to a fineness of 4000cm2/g. The company will additionally supply a packing plant module for bag and bulk loading.
Gebr. Pfeiffer said that in spite of delays to the unit’s commissioning due to coronavirus lockdown, it “has experienced specialists on site and is therefore able to support the customer in this phase.”
US: CalPortland has awarded a supply contract to FLSmidth for a new raw mill at its integrated Mojave plant in California. The scope of supply includes engineering, equipment and installation of a new OK 48-4 Raw Mill with a Condition Monitoring System and an ECS/ProcessExpert system. The mill is scheduled to be in operation in late 2021. No value for the current order has been disclosed.
“The new OK Raw Mill from FLSmidth will increase reliability and efficiency at our Mojave plant," said Bruce E Shafer, Senior Vice President for Cement Operations at CalPortland. It follows the purchase of a FLSmidth OK Cement Mill at the same plant in 2004. FLSmidth added that as both OK mills at the plant will share the same gearbox design, the unit will be able to streamline maintenance and manage inventory costs by sharing the one spare FLSmidth MAAG WPU-200 assembly.
Cement sales surge in Paraguay
19 May 2020Paraguay: Industria Nacional del Cemento (INC) has reported sales of 79,800 bags/day of cement between 4 May 2020 and 8 May 2020. Demand had collapsed in April 2020 due to restrictions on construction resulting from the coronavirus outbreak. Esmerk Latin American News has reported that newly reopened distributors collected their orders and that a number of customers purchased more than their usual volume in anticipation of a further easing of lockdown. INC has placed an order for 40,000t of imported clinker to help production to meet demand.
ACC orders new production line from KHD
18 March 2020India: KHD’s subsidiaries Humboldt Wedag India and Humboldt Wedag have signed a deal with LafargeHolcim’s subsidiary ACC to build a new raw meal grinding unit and a pyroprocessing line for an existing cement plant. The contracts also include the supply and installation of the electrical and instrumentation package for the entire cement plant. The entire contract package is worth over Euro35m.
Votorantim orders clinker cooler from Fons Technology
14 February 2020Tunisia: Brazil’s Votorantim Cimentos has ordered a clinker cooler and clinker roller crushers from Turkey’s Fons Technology International for an upgrade to its 1.2Mt/yr integrated Jbel Oust plant. Votorantim has been present in Tunisia since 2012 where it sells cement under the Jbel Oust brand.