Colombia: Finland’s Wärtsilä has signed a further four-year extension to its operation and maintenance (O&M) agreement with Cemex Colombia. The original agreement was started in 1998 and it has now been extended to the end of 2023. Cemex’s integrated Caracolito cement plant uses a 26MW power plant operating on five Wärtsilä 18-cylinder 34SG engines in V-configuration running on natural gas. Wärtsilä employs 15 personnel in the running of the power plant, all of whom were hired locally.