Cementos Portland Valderrivas may suspend cement production at Morata de Tajuña plant due to high costs

Print this page

Spain: Cementos Portland Valderrivas has warned the increased operating costs may force it to suspend production at its 2.8Mt/yr El Alto cement plant in Morata de Tajuña near Madrid. EuroNews has reported that energy prices more than doubled month-on-month to Euro300/MWhr on 21 October 2021 from Euro100/MWhr on 21 November 2021. Grinding operations use half of the plant’s electricity consumption.

Operations director Luis Herrers said "Because the cost of electricity has shot up by 300%, we have crossed a red line. Our production cost has exceeded our selling price.” He added “We are in a critical situation right now."

Last modified on 27 October 2021

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://globalcement.com/news/item/13169-cementos-portland-valderrivas-may-suspend-cement-production-at-morata-de-tajuna-plant-due-to-high-costs

© 2024 Pro Global Media Ltd. All rights reserved.