India: Prism Johnson has decided to move a proposed increase in its cement grinding capacity from its integrated Satna plant in Madhya Pradesh to a location in eastern Uttar Pradesh. It has done so in response to geographical demand. Previously the cement producer said it was going to add around 1Mt/yr of grinding capacity for a cost of US$34m with a commissioning date scheduled for September 2023. Now it wants to build a 2Mt/yr grinding unit in Uttar Pradesh for around US$67m with a commissioning date by December 2024.

Prism Johnson switches proposed grinding plant from Madhya Pradesh to Uttar Pradesh
URL: https://globalcement.com/news/item/13620-prism-johnson-switches-proposed-grinding-plant-from-madhya-pradesh-to-uttar-pradesh