IKN supplying cooler for upgrade at Małogoszcz cement plant

Print this page

Poland: Germany-based IKN says that erection works of a new IKN-supplied cooler are in progress at Lafarge Poland’s Małogoszcz cement plant. The Euro100m upgrade project is building a new 3700t/day clinker production line at the unit to replace the existing three lines. A new alternative fuels line will also be installed to reduce the plant’s CO2 emissions by 20% and its energy consumption by 33%. China National Building Material (CNBM) subsidiary Nanjing Kisen International Engineering was previously reported as being the lead contractor on the project.

Last modified on 26 April 2023

URL: https://globalcement.com/news/item/15638-ikn-supplying-cooler-for-upgrade-at-malogoszcz-cement-plant

© 2025 Pro Global Media Ltd. All rights reserved.