Venezuela: Cemento Andino has reported that work on its second production line at its cement plant in Candelaria, Trujillo is 70% complete. The new line will be completed in 2017. The US$103m line has a 1.12Mt/yr clinker production capacity and a 1.36Mt/yr cement production capacity. At present the cement plant has a clinker production capacity of 0.75Mt/yr. The plant was nationalised by the Venezuelan government in late 2006.