IKN provides detail on upgrade to HeidelbergCement’s Burglengenfeld plant

Print this page

Germany: IKN has revealed that first clinker was created on schedule at HeidelbergCement’s Burglengenfeld cement plant in April 2018 following an upgrade to one its kiln lines.

IKN was awarded a contract for engineering, supply and installation to upgrade the pyro-processing line to 4000t/day, from raw meal feeding to clinker discharge. The contract included integration engineering, supply and installation of add-on components for the raw meal grinding plant. The new production line comprises a two-string, five-stage preheater tower with inline calciner and Fire Bed Combustor for coarse refuse-derived fuel (RDF). IKN says that its most modern preheater and calciner design ensures minimum pressure drop at maximum performance and high efficiency. The kiln line has been designed for maximum use of a broad range of alternative fuels.

Last modified on 26 June 2018

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://globalcement.com/news/item/7698-ikn-provides-detail-on-upgrade-to-heidelbergcement-s-burglengenfeld-plant

© 2024 Pro Global Media Ltd. All rights reserved.