Pakistan: Maple Leaf Cement’s new production line at its Iskanderabad cement plant is expected to start production by mid-2019. It is building a new 7300t/day line at the site to increase its total production capacity to 18,000t/day. The cost is US$206m. Denmark’s FLSmidth is building the line. Approximately 66% of civil work has been completed and 14% of plant erection work was reported complete at the end of June 2018.