Maple Leaf Cement line at Iskanderabad on track to open in mid-2019

Print this page

Pakistan: Maple Leaf Cement’s new 7300t/day clinker production line at its Iskanderabad cement plant is expected to start in the second quarter of 2019. The project has a cost of just below US$200m, funded through bank loans, a right issue and internal revenue. Denmark’s FLSmdith is supplying the equipment and Descon Engineering holds the contract for civil construction and mechanical erection work. 70% of civil work and 30% of plant erection was reported completed by the end of September 2018.

Last modified on 17 October 2018