Installation work starts at L'Amalí plant upgrade project

Print this page

Argentina: China’s Sinoma International says that it has successfully lifted the first steel column of the pre-heater tower on a 5800t/day production line it is building at Loma Negra’s L'Amalí cement plant. The work in late December 2018 marked the start of the installation phase of the project. It is the subsidiary of China National Building Material’s (CNBM) first engineering, procurement and construction (EPC) project in South America. When the project was first announced in late 2017 it had a completion date of early 2020.

Last modified on 09 January 2019

Register for the Global Cement Weekly email newsletter

Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.

Register >

URL: https://globalcement.com/news/item/8573-installation-work-starts-at-l-amali-plant-upgrade-project