Cameroon: The electricity supply in parts of central and southern Cameroon has been disrupted whilst a substation at Nomayos near Yaoundé is connected to the main network. The disruption is necessary ahead of the commissioning of Cimencam’s Nomayos cement grinding plant, which is scheduled for the first quarter of 2019, according to Business in Cameroon. The new plant will have a production capacity of 0.5Mt/yr. It has an investment of around US$40m.