Libya: The Libyan Cement Company (LCC) says taxes, poor weather and local fighting have hampered its progress over the last year. The introduction of a 183% Foreign Exchange Tax in the last quarter of 2018 has tripled the price of imported spare parts, supplies and capital goods. This has delayed repairs to the cement producer’s plants. However the company believes that the tax may be lowered in the near future. A long and wet winter has also been blamed for reducing the demand for cement and reducing the company’s cash flow.
Fighting in Tripoli has affected the LCC’s operations in the east of the country with multi-month long interruptions to the supply of raw materials. It said that key roads have recently been re-opened following negotiations relieving the situation and that it hopes they will stay open.
The company said that it is still working towards a Euro200m upgrade project to its plant in Benghazi. The plan is to increase the unit’s production capacity to 3Mt/yr from 2Mt/yr.
Philippines: Eagle Cement’s sales rose by 28% year-on-year to US$202m in the first half of 2019 from US$157m in the same period in 2018. Its earnings before interest, taxation, depreciation and amortisation (EBITDA) grew by 21% to US$80.6m.
The company said it was on track to complete a 1.5Mt/yr grinding upgrade to its Bulacan plant in 2020. It added that it was secured approval for a permit to build a port terminal to support its new Line 4 production line at its Cebu plant. Once completed it expects to sell cement in the Visayas region by the end of 2020.
Mexico: Austria’s Unitherm Cemcon has been awarded the supply of an MAS DT burner to an unnamed cement plant in Mexico. The burner is designed for coal, natural gas and liquid secondary fuel operation. To optimise the maintenance work, the burner is equipped with a divisible jacket tube. A satellite burner, with the supplier’s adjustment system, will be mounted on top of the main burner to improve solid secondary fuel utilisation.
Loma Negra reports fire at L'Amalí cement plant
05 August 2019Argentina: Loma Negra says that a minor fire broke out at an auxiliary building for the second production line at the L'Amalí integrated cement plant on 1 August 2019. No casualties or injuries were reported in the incident. The subsidiary of Brazil’s InterCement said that the causes of the accident are yet to be determined but that no significant impacts are expected. The plant is currently being upgraded with a new production line that is scheduled for completion in early 2020.
India: Wonder Cement has launched the third production line at its Nimbahera plant at Chittorgarh in Rajasthan. The new 2Mt/yr integrated line had an investment of US$159m, according to the Hindu newspaper. The unit at Nimbahera now has a total production capacity of 9Mt/yr and the company also operates a 2Mt/yr cement grinding plant at Dhule in Maharashtra.
Sanjay Joshi, the executive director of Wonder Cement, said that he expected domestic cement demand to grow by 8% year-on-year in the 2019 – 2020 financial year. He added that, although the market was crowed, he thought that a new company could stand out if it delivered quality products.
Siberian Cement to upgrade automation systems
01 August 2019Russia: Siberian Cement is spending around Euro4m on upgrading the automated process control system (APCS) at its cement plants. The project, which is about half way along, is scheduled for completion in 2023.
UK: Cemex has invested around Euro1m on relocating and upgrading its Eversley ready-mixed concrete plant. The new plant will be located at the Bramshill Quarry in Hampshire reducing the need for truck journeys to the fomer site nearby. The unit is being replaced with a Liebherr 2.25 mobile mix plant. The plant will have a storage capacity of 300t of cement, and 240t of aggregates. It will increase production from 80m3/hr to 24m3/hr. The inclusion of a central mixer will also enable special products such as traditional sand cement screed and flowing screeds like Supaflo to be produced, increasing the product range available.
GCC’s half year results hit by poor weather in US
25 July 2019Mexico: GCC’s results for the first half of 2019 have been negatively affected by poor weather in the US. Its net sales grew slightly by 1.3% to US$404m from US$399 in the same period in 2018. Sales fell in the US but they rose in Mexico. Its earnings before interest, taxation, depreciation and amortisation (EBITDA) fell by 5% to US$109m from US$115m.
“While GCC’s US operations continued to be adversely impacted during the second quarter by an above average precipitation, below-average temperatures and construction labour shortages, the substantial backlog at our US operations underscores strong demand for our products. We’ve begun to reap the benefits early in the third quarter, as the US weather has finally cleared,” said Enrique Escalante, GCC’s chief executive officer (CEO). He added that the group had ‘successfully leveraged’ its new Trident plant in Montana and improved production levels at its Rapid City plant in South Dakota following a stabilisation process. Oil well cement shipments from its Chihuahua Plant to new terminal at Fort Stockton in Texas have also started.
Romania: Holcim Romania plans to spend Euro10m on automation and digitisation upgrades to its plants. The project will focus on its integrated plants at Alesd and Compulung, according to the Ziarul Financiar newspaper. The subsidiary of LafargeHolcim operates three cement plants in the country.
Keystone Cement to convert Bath plant to gas firing
23 July 2019US: Keystone Cement plans to convert its Bath cement plant in Pennsylvania to gas firing from coal. The project will cost US$2.2m, with a US$0.32m grant from the Pennsylvania Department of Community and Economic Development, according to the Express-Times newspaper. Gas supplier UGI Utilities will work with Keystone to install a new underground gas line from an existing substation to a new substation at the plant. The project is scheduled for competition by mid-2020.