Spasskcement runs kiln continuously for 330 days

Print this page

Russia: Spasskcement has run kiln two at its plant in Primorye continuously for a record of 330 days. This has beaten the previous best runtime of 324 days set in 2021. The kiln has now been shut down for scheduled repairs including replacing refractory lining and maintenance work on mechanical and electrical equipment. Work is scheduled to be completed by early May 2022.

 