IKN advances satellite replacement project at Fábrica Els Monjos

Print this page

Spain: IKN is progressing with its satellite replacement project at Grupo Cementos Portland Valderrivas’ Fábrica Els Monjos plant. The project includes the replacement of a cooler with an IKN grate cooler, with a new cooler building, burner and a complete vent air dedusting system. On pier two, IKN is fitting a new shell section and replacing the equipment on the pier, including a new base frame, rollers with bearings and CFU.

The company reported two major milestones: the new kiln section, including the tyre, was successfully lifted into place as one piece, shortening installation time; and the pre-assembly and positioning of the cooler, which was moved into its final position.