Iskitimcement commissions separator unit
08 June 2020Russia: Iskitimcement has completed the modernisation of the grinding plant at its 2.1Mt/yr integrated Iskitimcement plant in Novosibirskskaya following the installation of a closed-circuit dynamic separator and bag filter supplied by Christian Pfeiffer at a cost of US$3.69m. Iskitimcement director general Vladimir Skakun said that the upgrade aims, “to provide customers with separated cement that surpasses the quality of products produced with open-circuit grinding.”
The company said that the closed-circuit unit has increased productivity and reduced the temperature of cement. Dust emissions have fallen by over 90%, bringing the plant in line with current environmental strictures. “We are ready to meet the customers’ demand for quality products even at the peak of the construction season,” said Skakun.
Iskitimcement says that it is planning a modernisation of its stacks with the installation of new filters by 2024.
Spenner orders grinding plant from Christian Pfeiffer
18 January 2019Germany: Spenner has ordered a grinding plant from Christian Pfeiffer to be built at its main site in Erwitte. The unit will include a Ø 4.4 m x 14.0 m ball mill and a QDK 187-Z cross-flow rotating cage separator. In addition to the grinding plant, the engineering, procurement and construction (EPC) project also includes the planning of steel and concrete constructions as well as electrical switchgears.
Christian Pfeiffer is also responsible for the manufacture, delivery and optimum coordination of all associated components such as filter systems, bucket elevator, fans, chutes, samplers, reject transport and additional silos for additives. Staff training and performance test procedures carried out by the Christian Pfeiffer employees on site are also part of the commissioning of the plant.
YD Madencilik orders two grinding plants from Christian Pfeiffer
10 January 2019Turkey: YD Madencilik, part of Üstyapi Insaat Group, has ordered two grinding plants from Germany’s Christian Pfeiffer for a new cement plant in the Düzce region. Christian Pfeiffer will supply two parallel grinding plants, consisting of a roller press (2x 1450kW) and a ball mill (Ø 4.0 x 13.0m, 3200kW), supplemented by a KS200 static separator and a TFS 325-Z twin feed separator.
Each of the two plants ensures a production of 210t/hr of ordinary Portland Cement. Alternatively, the two grinding plants can also be operated separately to allow production of different types of cement. It is also possible to operate the roller presses or the ball mills in single mode. Delivery of components for the plants started in late 2018 and they are scheduled to be completed by the end of may 2019. Christian Pfeiffer previously worked with YD Madencilik in 2015.
Mordovcement officially opens grinding unit
09 October 2018Russia: Filaret Galchev, the chairman of Eurocement, and Vladimir Sushkov, the chairman of the government of the Republic of Mordovia, has officially opened a Euro65m grinding unit at the Mordovcement plant. The new grinding unit includes two ball mills with a production capacity of 2.6Mt/yr, a 50,000t clinker warehouse and rail and truck despatch silos. Eurocement used equipment from Christian Pfeiffer, Claudius Peters, Aumund and KHD for the upgrade project at its subsidiary.