Displaying items by tag: Ghori Cement
Ghori Cement plants double production capacity
29 July 2024Afghanistan: The National Development Corporation has announced that the production capacity of the Ghori Cement plants in Baghlan has increased to 700t/day from 350t/day previously, according to Bakhtar News Agency. This increase is reportedly due to attention from Islamic Emirate’s officials and the efforts of the National Development Corporation under the country’s new government.
Engineer Shafiullah Wahidi, director of Ghori Cement, revealed that 700 technical staff are working in three shifts to maintain production levels. Local residents and traders are urging further production increases to favour domestic products over foreign imports.
Ghori Cement production set to rise in Baghlan
23 July 2024Afghanistan: The Ghori Cement plant in Baghlan province plans to increase its production from 0.18Mt in 2023 to 0.2Mt in 2024 due to a growing demand for cement. Technical deputy of the factory, Sarbaz Banuzai, also revealed plans for a new cement plant capable of producing 1.3Mt/yr, which would stand adjacent to the current facility.
Factory workers voiced support for the expansion as a means to combat unemployment and boost local production.
Afghanistan: Ghori Cement says that its Baghlan cement plants currently produce 600t/day of cement, corresponding to annual production of 0.22Mt/yr. The producer states that production is restricted by shortages of electricity and vehicles. With regular supply of these, it would increase its production by 33% to 800t/day (0.29Mt/yr), according to the company.
Production at the Baghlan cement plants was previously suspended for four months in mid-2022 due to high coal prices. This was resolved when the government began supplying the plants with coal at a pre-agreed price. The plants then reopened with a daily production of 520t/day (0.19Mt/yr), up by 49% from 350t/yr (0.13Mt/yr).
The provincial government said that an upgrade with equipment from China and Iran since increased production by 15% to its present 600t/day (0.22Mt/yr).
Ghori Cement restarts production
17 August 2022Afghanistan: Ghori Cement has restarted production at its Baghlan plants near Pul-e-Khumr in Baghlan province after a stoppage of four months. Production halted at the units due to the high price of coal, according to Pajhwok Afghan News. The government is now supplying coal to the plants at a pre-agreed price. Other local news sources report that production has increased to 520t/day from 350t/day previously, following work on a variety of technical issues.
Ghori Cement achieves 0.2Mt/yr capacity
25 February 2020Afghanistan: Ghori Cement says that it has produced 18,600t of cement in January 2020, up by 400% from 3720t in January 2019. This would give the plant an annual production rate of 0.22Mt/yr, following ‘operational reforms and modernisation of spare parts.’ Arab News has reported that plans for the replacement of Ghori Cement’s Ghori, Pul-e-Khumri, cement plant with a new 0.4Mt/yr plant were interrupted by on-going civil strife in the region, north of the Afghan capital Kabul. Ghori cement plant general manager Riazudin Sharifi said, “Efforts are underway to further improve the capacity of the plant.”
Afghan government cancels contract for Ghori Cement
06 June 2018Afghanistan: The Ministry of Mines and Petroleum has cancelled the Afghan Investment Company’s (AIC) contract to operate Ghori cement factory in Baghlan province. The AIC has been accused of not meeting a contractual obligation to upgrade the plant, according to Salam Watandar radio. Minister Nargis Nehan said that the company has due to invest US$152m in the unit but that it had only spent US$51m on the project. In addition it had acquired an outstanding loan of US$13m from the ministry. Mehmood Karzai, brother of the former president Hamid Karzai, is a shareholder in AIC.