Cameroon: The electricity supply in parts of central and southern Cameroon has been disrupted whilst a substation at Nomayos near Yaoundé is connected to the main network. The disruption is necessary ahead of the commissioning of Cimencam’s Nomayos cement grinding plant, which is scheduled for the first quarter of 2019, according to Business in Cameroon. The new plant will have a production capacity of 0.5Mt/yr. It has an investment of around US$40m.
Electricity supply disrupted ahead of commissioning of Nomayos grinding plant in Cameroon
Written by Global Cement staff
Published in
Global Cement News
Tagged under
Register for the Global Cement Weekly email newsletter
Global Cement Weekly is Global Cement’s weekly email newsletter. Keep up to date with cement industry news, analysis, diary dates and news of people in the sector.