Displaying items by tag: preheater
Greece: Titan Cement Group has secured an EU patent for its robotic remote preheater system, previously installed at the company’s Kamari cement plant in Viotia. Titan Cement Group designed the system to maximise operational efficiency and safety.
The company carried out a Euro25m precalciner installation at the Kamari plant in 2021 – 2022.
GCC orders upgrade for Samalayuca plant from ThyssenKrupp Polysius
23 February 2022Mexico: GCC has signed an engineering, procurement and construction (EPC) contract with ThyssenKrupp Polysius for an upgrade to its integrated Samalayuca plant to increase clinker production capacity, raise the usage of alternative fuels and reduce emissions. The project includes the engineering, supply and modification of the preheater, including cyclones, and an extension to the calciner, with the installation of a Prepol SC-S type system to increase the utilisation of alternative fuels. The work also includes fitting a Polytrack type clinker cooler and the installation of a bypass system. The project will begin in 2022 with operations scheduled to start in the second quarter of 2023.
Senegal: France-based Fives has detailed the equipment that it will supply for its construction of a new 6500t/day kiln line at SOCOCIM Industries’ Rufisque cement plant in Dakar Region. The company says that it will supply a preheater, in-line Preca calciner, kiln, TGT filter and Pillard Novaflam burner.
SOCOCIM Industries’ parent company Vicat’s chair and chief executive officer Guy Sidos said “Vicat Group renews its partnership with Fives Group through this major project of building a new line with a strong local dimension, employing local workers and contractors.” He added “This plant will eventually eliminate the use of fossil fuels, reduce our energy consumption and support Senegalese local development, making a higher quality product while doubling our production capacity.”
ThyssenKrupp to upgrade Ciments Calcia’s Airvault cement plant
07 December 2021France: Germany-based ThyssenKrupp has won a contract for the installation of a new 4000t/day clinker line at Ciments Calcia’s Airvault cement plant in Poitou-Charentes. The supplier expects the new line to double the plant’s clinker capacity while also reducing its CO2 emissions. It is intended to replace the two existing lines at the site.
ThyssenKrupp will supply a 1200t/hr double-shaft hammer crusher, a longitudinal blending bed, a 370t/hr Quadropol QMR² 45/23 type vertical roller mill and a 10,000t tangential blending silo to process raw materials for the line. A single-string, five-stage Dopol type cyclone preheater with integral calciner will be supplied that is suitable to use with alternative fuels, with the possibility of conversion to oxyfuel in future. ThyssenKrupp plans to preassemble the preheater, reducing anticipated construction time ‘by several months.’ The plant also includes a Polytrack clinker cooler, a solid recovered fuel (SRF) preparation line and dedusting systems. Commissioning is scheduled for mid-2024.
No value for the project has been disclosed by Ciments Calcia or ThyssenKrupp. However, Ciments Calcia previously announced a proposed investment of Euro300m in January 2021.
Udayapur Cement launches upgrade to plant
19 November 2021Nepal: Udayapur Cement has commenced a US$4.2m upgrade and capacity expansion of its cement plant at Jaljale. The work includes replacing the shell of its 20m rotary kiln by the end of February 2021 and installing a reinforcement suspension preheater system, according to the Kathmandu Post newspaper. It will expand the plant’s capacity by 38% to 0.4Mt/yr from 0.29t/yr. The plant’s current equipment dates to 1988. Company spokesperson Laxman Pokharel said "Since the machines are old, we face frequent problems." He added that this has led to increased costs.
The Nepal government has agreed to loan Udayapur Cement US$34.4m, 80% of the project’s budget.
South Africa: Sephaku Cement has reported a second unexpected kiln stoppage at its integrated Aganang plant in Lichtenburg. It attributed the second delay on the need for a repair to the inside of the kiln. The second stoppage started on 16 October 2021 and was expected to be completed by 26 October 2021. Previously, the kiln was stopped from 30 September 2021 to 6 October 2021 due to preheater refractory material damage caused by a corrosive element in one of the raw materials being used. The producer said that the raw material was subsequently replaced with an alternative option. The subsidiary of Nigeria-based Dangote Cement said that the outages were expected to reduce its sales volumes.
FLSmidth to supply 11,500t/day kiln line for Shree Cement’s upcoming Nawalgarh cement plant
12 October 2021India: Shree Cement has hired FLSmidth to supply a 11,5000t/day kiln line for its planned Nawalgarh, Rajasthan, cement plant. The line will consist of a six-stage preheater and a three-support kiln. The supplier will also deliver an OK vertical roller mill, which it says has a 5 – 10% lower energy consumption than a standard vertical roller mill. The project focuses on sustainable productivity and emissions control. Shree Cement has opted for JetFlex burners to give the lowest possible nitrous oxide emissions for various fuel types.
Shree Cement managing director Prashant Bangur said “Based on the experience of working with FLSmidth on the installation of a 9,000t/day pyro system at the Raipur, Chhattisgarh, cement plant earlier this year, we felt confident about approaching Carsten Riisberg Lund and his team regarding the Rajasthan project.” He added “Being recognised as a Sustainability Champion by the World Economic Forum is a testament of our emphasis on sustainability at every stage of our operations. The new line will push that agenda even further in terms of lowering the benchmarks on energy consumption and emissions, and thereby reducing our environmental footprint.”
FLSmidth also supplied a second OK mill for Shree Cement’s operations in Kolkata, West Bengal.
IKN to equip new line at Qizilqumsement cement plant
24 March 2021Uzbekistan: Germany-based IKN has secured a contract for process integration and equipment design for a new kiln line at Qizilqumsement’s Qizilqumsement cement plant. The supplier’s remit includes the pyroprocessing line, preheater, kiln and cooler including ID fan, kiln drive and burners. It plans to use a six-stage preheater, the region’s first. Commissioning is scheduled for 2022.
State Committee on Ecology and Environmental Protection suspends cement production at SingLida plant
26 February 2020Uzbekistan: The State Committee on Ecology and Environmental Protection (SCEEP) has suspended operations at SingLida’s 0.1Mt/yr integrated Ahtachi plant in Andijan region. Trend News has reported that, following an audit of clinker production between 12 February 2019 and 21 February 2019, the cyclones had failed to meet lawful standards of dust collection. Rates varied between 53% and 61% dust collection, compared to a design capacity of 100%. The government body said that it had given ‘instructions for prompt elimination of deficiencies and reduction of pollutant emissions into the air,’ and has suspended operations of the clinker line and mill until such a time as the problem is resolved.
Kerbulak plant commissioning expected March 2020
27 December 2019Kazakhstan: The government of the Almaty region in eastern Kazakhstan has announced that the construction of the Kerbulak cement plant, which began in May 2018, ends 2020 at 97% completion. The government and a Singaporean private company have installed preheaters, crushers, raw materials warehouses and a 25MW substation. The launch date of the plant is in March 2020. Of its 1.2Mt/yr cement yield, 80% will be sold on the domestic market, with 20% leaving Uzbekistan for Mongolia and neighbouring countries including China.