Boral completes maintenance at Berrima plant

Print this page

Australia: Boral's Berrima cement plant team has successfully concluded its annual kiln shutdown and maintenance period. The producer invested US$13.1m and 100,000 working hours over a period of three weeks. The project required coordination with 50 different contracting companies to undertake mechanical repairs and replace the kiln refractory, which is crucial for protecting the kiln shell from heat damage and ensuring operational safety. Employing Cement 4.0 technology and advanced diagnostic tools, the team efficiently identified the necessary repairs. About 300 employees and contractors were engaged in the specialist tasks, facilitating a rapid resumption of kiln operations.

Last modified on 28 February 2024