The Gambia: A recent cement shortage in the Greater Banjul Area and West Coast Region has been attributed to delays at the country’s main port, according to Omar Badjie, director of industry at the Ministry of Trade, Industry, Regional Integration and Employment. The disruption reportedly stemmed from a backlog at the Banjul port that left a key shipment from cement supplier Jah Oil waiting offshore.
“The issue wasn't production capacity,” Badjie said. “The port was congested, and Jah Oil's vessel had trouble berthing. That put pressure on the two other cement plants, Salam and Gacem, which couldn't meet the market's demand on their own.”
The government expedited a berth for Jah Oil's vessel, which docked last week with 38,000t of cement. However, supply constraints persist, with contractors reporting stalled projects and inflated prices.