Nepal: The Nepal Electricity Authority (NEA) has completed and commissioned a switching station to supply power for Huaxin Cement and Vaidya Group’s upcoming Dhading cement plant in Rorang. The Republic newspaper has reported that, when operational, the plant will receive 20MW of power via the switching station. Two transmission lines with capacities of 33kV and 11kV connect the facilities.
The US$125m Dhading cement plant awaits commissioning following the completion of its construction in August 2021.