It’s been a good week for carbon capture projects in Europe with the announcement of who the European Union (EU) has selected for a grant from its Innovation Fund. 17 large-scale projects have been pre-selected for the Euro1.8bn being doled out in the second round of awards. On the cement and lime sector side there are four projects. These include projects at Holcim’s Lägerdorf cement plant in Germany, HeidelbergCement’s Devnya Cement plant in Bulgaria, Holcim’s Kujawy plant in Poland and Lhoist’s Chaux et Dolomites du Boulonnais lime plant in France. Large-scale in this instance means projects with capital costs over Euro7.5m. To give readers some sense of the scale of the projects that the EU has agreed to pay for, if the funding was shared out equally between the current bunch, it would be a little over Euro100m per project. This is serious money.
Devnya Cement’s ANRAV carbon capture, utilisation and storage (CCUS) project in Bulgaria has received little public attention so far so we’ll look a little more closely at this one first. No obvious information is available on what capture technology might be in consideration at the plant. HeidelbergCement’s leading experience in carbon capture technology at cement plants gives it a variety of methods it could use from a solvent scrubbing route to something less common. What the company has said is that, subject to regulatory approval and permitting, the project could start to capture 0.8Mt/yr of CO2 from 2028.
What has also been revealed is that the project is linking up via pipelines to a depleted part of the Galata gas field site in the Black Sea. Oil and gas company Petroceltic Bulgaria is a partner and the aim of the project is to start a CCUS cluster in Eastern Europe. with the potential for other capture sites in Romania and Egypt to join in. This is noteworthy because much of the focus for the burgeoning cement sector CCUS in Europe so far has been on usage on local industrial clusters or storage in the North Sea.
The other new one is the Go4ECOPlanet project at Holcim’s Kujawy plant in Poland. Lafarge Cement is working with Air Liquide on the project. The latter will be providing its Cryocap FG adsorption and cryogenics technology for direct capture of flue gas at the plant. The transportation of the CO2 is also interesting here as it will be by train not pipeline. Liquid CO2 will be despatched to a terminal in Gdańsk, then transferred to ships before being pumped down into a storage field under the North Sea.
Turning to the other two grant recipients, the Carbon2Business project plans to capture over 1Mt/yr of CO2 using a second generation oxyfuel process at Holcim Deutschland’s Lägerdorf cement plant. This project is part of a larger regional hydrogen usage cluster so the captured CO2 will be used to manufacture methanol in combination with the hydrogen. Finally, Lhoist’s project at a lime plant in France is another team-up with Air Liquide, again using the latter’s Cryocap technology. The capture CO2 will be transported by shared pipeline to a hub near Dunkirk and then stored beneath the North Sea as part of the D'Artagnan initiative. Around 0.61Mt/yr of CO2 is expected to be sequestered.
The key point to consider from all of the above is that all of these projects are clear about what is happening to the CO2 after capture. The days of ‘carbon capture and something’ have thankfully been left behind. CO2 transportation infrastructure is either being used or built and these cement plants will be feeding into it. This will inevitably lead to questions about whether all these new CO2 networks can support themselves with or without EU funding but that is an argument for another day.
Finally, in other news, four residents from the Indonesian island of Pulau Pari started legal proceedings against Holcim last week for alleged damages caused by climate change. Industrial CO2 emissions are unquestionably a cause of this along with other sources but what a court might think about this remains to be seen. Yet, it is intriguing that the plantiffs have decided to go after the 47th largest corporate emitter rather than, say, one of the top 10. Regardless of how far the islanders get this is likely not to be last such similar attempt. If the case does make it to court though it seems likely that Holcim will mention its work on CCUS such as the two projects above. Only another 200-odd cement plants in Europe to go.