Ethiopia: Lemi National Cement Factory’s construction of its upcoming Lemi cement plant is 70% complete and will conclude in time for inauguration of the plant on schedule in early 2024. Ethiopian News Agency has reported that construction of the 8Mt/yr plant’s preheater frames and rotary kilns finished on 28 November 2023. China-based Sinoma International Engineering is carrying out the project, which has a total cost of US$600m. Lemi National Cement Factory is a joint venture of local conglomerate East African Holding and West China Cement subsidiary West International Holding.
Lemi National Cement Factory’s 8Mt/yr plant on track for inauguration in early 2024
Written by Global Cement staff