India: Humboldt Wedag has overseen the pouring of 109,000m³ of reinforced concrete at the Goldcrest greenfield integrated cement plant over the past 14 months, with major civil work on process buildings and clinker production due to complete by 15 September 2026, with 3000m³ remaining. Mechanical erection is due to be completed by November 2026 and cement grinding is scheduled for February 2027, according to a LinkedIn post by Ashok Dembla from Humboldt Wedag. Global Cement previously reported in May 2025 that the plant will have a cement capacity of 4.5Mt/yr and a clinker capacity of 3.5Mt/yr. Humboldt Wedag India was appointed engineering, procurement and construction contractor and targets completion by March 2027.