India: Prism Johnson has added a proposed addition of 1Mt/yr to the cement grinding production capacity at its 5.6Mt/yr integrated plant at Satna in Madhya Pradesh. The project is expected to cost around US$34m with a scheduled commissioning date by September 2023. In January 2021 the cement producer said it was considering investing US$19m in a 0.9Mt/yr expansion to the Satna plant with a commissioning date by December 2021.