Bangladesh: Chhatak Cement’s plant in Sunamganj remains idle despite construction completing in March 2023, with production suspended due to unresolved gas and limestone supply issues, according to the Prothom Alo newspaper. The plant project began in 2016. New details confirm that the Bangladesh government has approved subcontracting of a cross-border ropeway to import limestone from India. Local firm Komorah Limestone Mining Company (KLMC), which already supplies limestone to Chhatak Cement, is in talks regarding the role. China-based contractor for the project, Nanjing Sea-Hope Cement Engineering, has agreed ‘in principle’ to this handover as of 18 March 2025, according to Chhatak Cement managing director Abdur Rahman.
Project officials stated that, once the new plant begins operations, it will be capable of producing 1500t/day of clinker and 500t/day of cement, triple its previous capacity. Reporters conducted a site visit on 8 April 2025, observing that a jetty had been constructed on the riverbank to unload clinker from the plant for grinding elsewhere. A conveyor system has been set up to move cement bags directly from the plant to transport, and a new conveyor belt has also been installed alongside the existing belt.