Egypt: ASEC Minya (formerly the Arab National Cement Company), part of ASEC Cement, has started the production of clinker at its 2Mt/yr cement plant in Minya. Cement production at the US$360m plant is expected to start by the end of June 2013.
"We are extremely proud to have been able to see this project through to completion despite the challenging operational environment," said ASEC Cement CEO Giorgio Bodo. "Security issues, fuel scarcity and a general environment of instability resulted in major setbacks and required us to come up with creative ways of ensuring that the project did not come to a halt." Construction on the plant began in December 2010 but work was interrupted by the Egyptian Revolution in January 2011.
ASEC Minya will produce Portland Grey cement using limestone in Minya governorate. The plant has created 400 direct and 800 indirect jobs in Minya.
ASEC Minya will be connected to the national grid via a 42km transmission line that connects the plant to the Samalloot power station. A slow regulatory approval process will not allow the plant to have a connection to the electrical grid until the end of 2013 but in the meantime ASEC Minya has come up with a temporary solution with rented generators to provide power to the plant.
ASEC Minya is the second greenfield cement plant to be launched by ASEC Cement in five years. The first was Takamol Cement in Sudan, a 1.6Mt/yr plant that began production in November 2010.