Ethiopia: A TEC has released progress information on contracts to provide an alternative fuel system, which can process sesame straw and stalks, and a cement big-bag filling station for Messebo Building Materials Production in Mekelle. Both commissions were awarded in the first quarter of 2013 and local manufacturing and the erection will be performed by Mesfin Industrial Engineering PLC, a sister company of Messebo.
Installation of the alternative fuels system will start in the fourth quarter of 2013 with a planned start-up in the first quarter of 2014. Collection and preparation of straw and the production of bales will take place at Kafta Humera. The first phase of the project includes building a baling capacity of 50t/hr and an alternative fuel feeding capacity to the calciner of 10t/hr at the cement plant in Mekelle. A future upgrade, phase two, will scale the system up to a baling capacity of 71t/hr and an alternative fuel feeding capacity of 20t/hr.
The new station for big-bag filling will be installed at the cement plant in Mekelle. The system will consist of three filling stations in modular design. Each station can handle 15 bags/hr. A total number of 45 big-bags/hr with an overall capacity of 90t/hr can be reached. The big-bag filling station will be installed and commissioned at the end of 2013.