Tanzania: Dangote Cement has applied for a licence to build a 75MW coal-fired plant in Tanzania that would power a US$500m cement plant now under construction, Tanzania's energy watchdog has reported.
"Dangote Industries applied for a 75MW electricity generation licence to build, own and operate a coal-based captive power plant adjacent to its cement plant," the state-run Energy and Water Utilities Regulatory Authority (EWURA) said. All the generated electricity will be used to run the plant and associated utilities.
"Any interruption in power supply or unstable voltage/frequency causes extensive damage to the refractory and also to the rotary kiln parts. Refractory failures cause production shutdowns varying from 15 to 30 days and unscheduled use of costly imported refractory bricks," the regulator added.
The Dangote cement plant in southern Tanzania is scheduled to be commissioned in the second half of 2015. With a capacity of 3Mt/yr it will supply Tanzania's domestic market and export to landlocked nations in the region.