Kenya: According to Reuters, Kenyan cement producers have said that they are being left out of a US$3.8bn railway project that China Rail & Bridge Corporation (CRBC) is building, after the company gave an assurance it would source all of the raw materials domestically.
Companies including Lafarge South Africa's Kenyan unit and ARM Cement have asked Kenya Railways Corporation, the implementing agency, to provide clarity on CRBC's local procurement plans, five months after work on the project started, according to ARM Cement CEO Pradeep Paunrana. Kenya Ports Authority data show that CRBC has imported at least 7000t of cement so far in 2015.
"There was an assurance that all of the cement would be supplied by local producers," said Paunrana, who is also chairman of the Kenya Association of Manufacturers. "There has not been transparency on how much we will supply and we don't understand why they are importing cement when we can clearly supply cement to their specifications."
The 'Standard Gauge Railway Project' (SGR) is Kenya's biggest investment in infrastructure since it gained independence from Britain in 1963. The Export-Import Bank of China is funding 90% of the railroad, which will connect Nairobi to Mombasa, East Africa's biggest port. It is scheduled to be completed by 2017. Kenya's Treasury is pinning its 7% growth target for 2015 partly on activities generated during construction of the 609km link. In June 2015, treasury secretary Henry Rotich allocated US$1.46bn to the project for the 2015 - 2016 financial year.
The SGR project requires 1Mt of cement, all to be sourced in Kenya, according to a master list of supplies that the manufacturers' association was given by CRBC. Kenya is a higher cost producer of cement than China and imports for the project are duty-free, according to Paunrana. Kenya Railways spokeswoman Mary Oyuke has said that the company isn't importing cement because the material is available locally and ARM and Bamburi are already supplying the project.
ARM and other producers, including Lafarge's unit Bamburi Cement, have upgraded their plants to produce the 52.5 grade cement required by the contractors. The enhancements cost 'several million dollars' and were commissioned on the understanding that CRBC would buy the cement from domestic manufacturers. "We undertook significant investments in an endeavour to seamlessly supply cement to the project, including long-term agreements with transport companies to make deliveries," said Bamburi CEO Bruno Pescheux. "It is our hope that the project will continue to purchase cement locally rather than import, in light of the above investments." Bamburi supplied 20,000t of cement in April 2015.