Mexico/Qatar: Fives has released information on cement plant projects in Mexico and Qatar. It commissioned a second FCB Horomill unit on 31 January 2017 at the cement grinding plant of Cementos Fortaleza, as part of the new 3300t/day complete line under construction at the Tula cement plant in Hidalgo. The first unit was commissioned in early December 2016.
Fives FCB was awarded the engineering, procurement and construction (EPC) contract from Cementos Fortaleza in mid-2015 for the design, supply, erection and commissioning of the cement production line. It includes a burning line using a FCB Kiln, FCB Zero-NOx Precalciner, FCB Preheater and Pillard Novaflam burner; raw meal and cement grinding plants using FCB Horomill and associated FCB TSV™ Classifiers; and a petcoke grinding plant using a FCB B-mill and associated FCB TSV Classifier. The FCB Horomill raw meal grinding plant and FCB Kiln are scheduled for commissioned in the second quarter of 2017.
In Qatar, Fives commissioned a cement milling unit on 6 February 2017 for Qatar National Cement Co.'s fifth production line in Umm Bab. This follows the commissioning of another mill at the site on 25 January 2017.
The mills are part of a 5000t/day production line that Fives is building for the client covering raw material preparation to cement despatch. The equipment ordered includes one 6400 kW FCB B‑mill with a FCB TSV7500 Classifier for the raw meal grinding plant, one five-stage FCB Preheater and a FCB Zero-NOx Precalciner, along with a FCB Kiln for the burning line, two TGT process filters and two 4200 KW FCB B‑mills with their FCB TSV4000 Classifiers for the cement grinding plant.