Displaying items by tag: Nepal Electricity Authority
Nepal: Udayapur Cement Industry resumed operations on 24 April 2025, despite ongoing legal disputes and internal administrative obstructions, according to acting general manager Mahesh Sah. The plant ceased all activities in late November 2024. It began kiln firing at 10:40am local time and expected clinker production to begin after eight hours of machine operation.
The plant aims to produce approximately 400t/day of clinker. Coal and dinepalesel stocks are expected to last 12 days. Sah noted that coordination has been made with the Nepal Electricity Authority, which has assured uninterrupted power supply despite outstanding dues. Udayapur Cement, a fully state-owned enterprise, has a daily production capacity of 800t/day.
Hetauda Cement Industry to resume operations
26 March 2025Nepal: Hetauda Cement Industry will restart production in the first week of April 2025 after completing machinery maintenance, securing raw materials and reaching agreement with employees, according to local news reports. The state-owned plant halted production on 1 October 2024. It has a capacity of 16,000 bags/day.
Acting general manager Nabin Kumar Karna said “It took some time to repair the machinery as it was old and damaged. The machines were installed when the industry was first established in 1977, and replacing them immediately was not possible due to financial constraints. Currently, we have about 100t of coal in stock, and more is expected to arrive starting tomorrow, so the raw material supply is not a major concern.”
Karna said that the electricity issues the company had previously faced had been resolved, and the Nepal Electricity Authority were ‘committed’ to providing a regular electricity supply.
Hetauda Cement Industry faces disruption
07 January 2025Nepal: Hetauda Cement Industry has paused production for nearly three months, with no clear timeline for the return to regular cement production, according to Khabar Hub news. The company has cited a need for repairs to various equipment and the installation of new machinery as the cause.
Basanta Raj Pandey, general manager, said that operations depend on confirmation of a regular 8MW power supply from the Nepal Electricity Authority. Ongoing negotiations with the NEA have reportedly yet to resolve daily power cuts, which have delayed the repairs and installations, which are expected to take several more weeks. The company once produced 18,000 bags/day of cement, but now produces just 10,000 bags/day due to deteriorating equipment. A bidding process for the procurement of 4000t/day of coal has now begun.
Nepal: The Nepal Electricity Authority (NEA) has agreed to supply ten industrial users, including cement producers, with an additional 151MW of electricity as part of a drive to increase domestic consumption. The cement producers concerned include Maruti Cement, Huaxin Cement, Hongshi Shivam Cement and Arghakhanchi Cement, according to the Republica newspaper. The other industrial users are mostly steel producers. In addition another 111MW is in the final stages of being allocated by the NEA to seven other industrial plants and a further 99MW has been identified for further distribution to industrial users. The government-supervised power supplier and distributor has identified around 500MW of wasted electricity supply due to low domestic consumption and a lack of transmission lines.
Nepal Electricity Authority completes switching station for Huaxin Cement and Vaidya Group’s Rorang cement plant
18 October 2021Nepal: The Nepal Electricity Authority (NEA) has completed and commissioned a switching station to supply power for Huaxin Cement and Vaidya Group’s upcoming Dhading cement plant in Rorang. The Republic newspaper has reported that, when operational, the plant will receive 20MW of power via the switching station. Two transmission lines with capacities of 33kV and 11kV connect the facilities.
The US$125m Dhading cement plant awaits commissioning following the completion of its construction in August 2021.