Pakistan: Maple Leaf Cement has ordered a 7300t/day cement production line from FLSmidth. The plant will be located in Iskanderabad in the Mianwali District. The order has been placed at above Euro75m and it will be completed by the end of 2018.
The order will include an ATOX 52.5 vertical mill for raw grinding, an ATOX 27.5 vertical mill for coal grinding, an EV 200x300 Hammer Impact Crusher, stacker and reclaimer systems for storage, a ROTAX-2 rotary kiln with low NOx ILC calciner, a FLSmidth Cross-Bar cooler, a JETFLEX burner and two OK 39-4 vertical mills for cement grinding.
"This is the latest project to underline FLSmidth's strength as the leading supplier of the most productive and energy-efficient equipment and technology - and our position as the preferred supplier of complete production lines to the Pakistani cement industry," said FLSmidth’s Group Executive Vice President, Cement Division, Per Mejnert Kristensen.